Hindustan Urvarak & Rasayan LTD. (HURL)

 Revival of Gorakhpur, Sindri and Barauni units by HURL

Government mandated revival of Gorakhpur, Sindri and Barauni units through nomination basis by forming a Joint Venture company of nominated PSUs i.e.  NTPC, IOCL and CIL. Accordingly, a Joint Venture company named Hindustan Urvarak & Rasayan Limited (HURL) was incorporated with equity participation of 29.67% each by NTPC, IOCL and CIL and 11% by FCIL for setting up gas based Ammonia urea plant of 12.7 LMTPA capacity each at Gorakhpur, Sindri and Barauni. The Gorakhpur Plant has been commissioned on 7th December, 2021. Barauni and Sindri Plants have started urea production on 18.10.2022 and 05.11.2022 respectively . The synopsis of Gorakhpur, Sindri and Barauni plants of HURL is given below: -

S.No.

Description

Gorakhpur Project

  Sindri Project

Barauni Project

1

Location

Gorakhpur (UP)

Sindri (Jharkhand)

Barauni (Bihar)

2

Capacity

2200 MTPD Ammonia,   3850 MTPD Urea

2200 MTPD Ammonia,   3850 MTPD Urea

2200 MTPD Ammonia,   3850 MTPD Urea

3

Annual urea Production

(Neem coated urea)

 

12.7 Lakh MT

12.7 Lakh MT

12.7 Lakh MT

4

Feed Stock – NG

2.21 MMSCMD

2.21 MMSCMD

2.21 MMSCMD

5

Source of Natural Gas

Jagdishpur – Phulpur-

Haldia Pipeline

Jagdishpur – Phulpur-

Haldia Pipeline

Jagdishpur – Phulpur-

Haldia Pipeline

6

Source of water

Rohini/Rapti River through Chilwa Tal

Damodar River

Ganga River

7

Foundation Stone Laying by Hon’ble PM

22nd Jul 2016

25th  May 2018

17th  Feb 2019

    8

Date of Commissioning / Start

  7th Dec 2021

05.11.2022

18.10.2022