Statement - I

 

PROJECT / SCHEMES UNDER IMPLEMENTATION / PROPOSED FOR IMPLEMENTATION & PROVIDES FOR IN THE BUDGET

( Rs. in Crores )

Sl. No. DETAILS TOTAL COST EXPENDITURE UPTO 97-98 (ACTUAL) OUTLAY 98-99 PROPOSED 99-2000 START OF COMM PROD REASON FOR VARIATION BE/RE 97-98
ORIGINAL LATEST NOW ANTICI- PATED B.E. R.E. ORIGINAL ANTCP
A Continuing schemes
1 Aonla expansion project 939.54 960 954.67 937.62 0.00 17.05 0.00 1.1.96/ 1.10.96 25.12.96 Actual started comm prod
2 Kandla retrofit/expansion 7.55 212.20 212.20 40.22 100 120 51.98 1996-97/ 1.7.98 22.10.99 Based on date of award of contract
3 Kandla - Jetty 0.00 24 24 15.27 6.53 8.73 0.00 1998-99 1998-99 Actually strd comm prod
4 Kalol expansion project 120 119.08 149.71 147.57 0.00 2.14 0.00 1.3.97 TO 20.1.98 31.8.97 Do
5 Phulpur expansion project 600 993.6 1190 1146.85 52.38 43.15 0.00 1.7.98/ 20.1.98 22.12.97 Do
6 Operational flexibility and energy saving for Aonla-I 19 19 16 16 0 0 0 96-97 97-98 Completed
Total of cont. schemes 1686.09 2327.88 2546.58 2303.53 158.91 51.99 -

-

-

B New schemes
1 Nelore fertilizers Project 1468.20 1568.70 1568.7 5.31 150 2 10 1.4.99 2000-02 Zero date not yet fixed
2 Phos. acid project/ Joint Venture for Nitro Projects Outside India
A)  For Nitrogenous fert. 317.72 120 236.11 0.00 10 5.5 93.70 1.4.99 2002-3 Zero date not yet fixed
B)  For Phosphoric Acid 0.00 100 100 0.00 50 50 50 1998-99 2000-1 Do
3 Diversification/modernisation 0.00 200 30 0 10 10 10 2001.-2 2001-2
4 Fert.   Proj. - East Zone 0.00 482 273 0.00 0.00 0.00 0.00 2003-4 2004-5
5 Purchase of Naphtha Wagons 0.00 0.00 20.00 0.00 20.00 20.00 0.00 1998-99 1998-99
New scheme total 1785.92 2470.70 2227.81 5.31 240 87.50 163.70 - -
C Science And Technology (Research & Development) 3 4.2 12.14 0.14 3 3 3 - -
D Renewals & replacements 73 87.99 294.29 64.29 40 50 60 - -
Total - IFFCO 3548.01 4890.77 5080.82 2373.27 441.91 331.56 278.68 - -
 