| CHAPTER-III
APPRAISAL
REPORTS OF MAJOR PROJECTS/PROGRAMMES
IFFCO's KANDLA PHASE-II
DAP/NPK EXPANSION PROJECT
The approved
capital cost of the Kandla (Phase-II) DAP/NPK
Expansion Project of IFFCO is Rs.212.20
crore, including a foreign exchange component
of Rs.18.10 crore. It is being funded with a debt
equity ratio of 1:1. The zero date of the project
was 22.1.1997 with a project icompletion schedule
of 33 months.The project is scheduled to go into
commercial production on 22.10.1999. After completion,
the capacity of the existing plant will increase
by about 3.70 lakh TPA of NPK and 2.27 lakh TPA
of DAP. The project is progressing as per schedule.
The actual expenditure incurred on the project
till October, 1998, was Rs.79.01 crores
and the overall physical progress was 68.01%. |